The Process

Day 1 - Step 1

We come to your home or condo and ask you to have your personal belongings removed from the bathroom prior to our arrival.

Step 2

We will remove your shower enclosure and take it away for disposal.

Step 3

All of your wall tile, shower floor tile, wall boarding and shower floor curb will be removed and disposed of.

Step 4

At this point, we will give the shower a thorough inspection to make sure we don't have any wood rot or mildew issues. We then allow the shower to air out and dry for the remainder of the day.

Day 2 - Step 5

The plumber will arrive and inspect the floor drain, change it if it's necessary and install a new shower valve which we highly recommend is done at this point doing your shower replacement.

Day 3 - Step 6

On day three, the tile crew will arrive and install the new half inch cement wall boarding and build a new shower floor and reinforced shower curb.

Day 4 - Step 7

On day four, the crew will start installing your tile of choice on to the walls and waterproof the bottom portion of the wall and shower floor before the end of the day.

Day 5 - Step 8

On day five, the tile crew will finish off the installation of the tile on the wall and shower floor. The shower curb then gets capped with a piece of marble. Next, the tile will be grouted and washed cleaned. The work area will be cleaned up and all of the garbage will be disposed of off site.

The shower is now finished and ready to be measured and fitted with the new shower door.